Can I delink the Finish Date from Duration in a Schedule
craigwaco
✭✭✭
Hi,
I need to delink the Duration column from the Finish date in a schedule.
I'm creating a master / roll up schedule that is linking from multiple sheets, however I can't link the finish date as it's greyed out. It's dependent on the duration.
Is this possible? Are there any work arounds?
Best Answer
-
In gantt view there is a gear in the top right. click that and you can change dependencies.
Answers
-
In gantt view there is a gear in the top right. click that and you can change dependencies.
-
Thank you @L_123 that did it. I looked in the settings, but I didn't realize that turning off dependencies would allow me to link it.
thank you!