Welcome to the Smartsheet Forum Archives


The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.

Resource mgmt - Allocating less (or more) than 8 hours a day for a resource

All.

My team spends 15% of their time in other activities like meetings, career development, system support, etc. I would like to use Smartsheet resource mgmt functionality but only allocating approx 6 hours a day for my resources. How can I do that?

Thanks

Comments

  • Travis
    Travis Employee
    edited 07/09/15

    As of right now, it isn’t possible to set a working day to 6 hours, however after our release this Saturday (July 11th) you will have the ability to set how long your working days are. Stay tuned for more information on this functionality! 

This discussion has been closed.