Getting a group of predecessors to fill in sections
I have the same set of subtasks in my project that repeat over and over. I have predecessors set up for the flow and I want to copy and paste it down the sheet and have the associated rows update to the new numbers. Everything I try just copies and pastes the original set of row numbers. Updating every row manually is going to take forever.
Best Answer
-
Hi @Ksephora
As long as the Child Rows are referencing each other (meaning the Predecessors are under the same Parent) then the Predecessors will update when you Copy/Paste to reference the newly pasted rows.
However if any of the references are outside of that specific Parent, then the Predecessor number will stay associated with that external row number, does that make sense?
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
Hi @Ksephora
As long as the Child Rows are referencing each other (meaning the Predecessors are under the same Parent) then the Predecessors will update when you Copy/Paste to reference the newly pasted rows.
However if any of the references are outside of that specific Parent, then the Predecessor number will stay associated with that external row number, does that make sense?
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
Thanks, that's very helpful!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives