Is there a way to plug in the Working Days criteria (non-working days, holidays, etc) without turning on Dependencies? I'm trying to build a sheet that recognizes weekends and company holidays as non-working days, but I don't need Predecessors or Duration columns.
In the past I've enabled Dependencies then literally blacked out the unneeded columns and hid them. However, I'm now working on a sheet that has many columns and rows. I don't want the sheet to have anything extraneous if it doesn't need to.
Thanks,
Shannon
Comments
-
Based on this article by Smartsheet you do have to enable dependencies to enable working days.
https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
Sorry - hiding the columns might be your best bet.
-
Shannon,
Yes you can.
See my post here:
http://ronin-global.com/2017/06/23/smartsheet-using-working-days-without-dependencies/
Craig
-
Sneaky sneaky. Remembering this one. Thanks Craig for showing us a work around.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives