Predecesor lag using calendar days regardless working days setup
Hello everyone.
This time I ask the community for help to assist me on how to use lag for precedecesor in Smartsheet. On some tasks, I need to add lag using calendar days instead of working days setup for the sheet.
At the moment I have been manipulating lag to estimate calendar days target. However, I am wondering if there is a more elegant way to do it.
Thank you.
Best Answer
-
Hi @Camilo P.
The way you're currently doing it is what I would suggest; Smartsheet does not have a way of adding Elapsed days (calendar days) to the Lag or Lead time in a Predecessor field.
Please add your vote and voice to this Product Idea thread, here: Elapsed Days in Predecessor Field
Cheers,
Genevieve
Need more information? π | Help and Learning Center
γγγ«γ‘γ― (Konnichiwa), Hallo, Hola, Bonjour, OlΓ‘, Ciao!π | Global Discussions
Answers
-
Hi @Camilo P.
The way you're currently doing it is what I would suggest; Smartsheet does not have a way of adding Elapsed days (calendar days) to the Lag or Lead time in a Predecessor field.
Please add your vote and voice to this Product Idea thread, here: Elapsed Days in Predecessor Field
Cheers,
Genevieve
Need more information? π | Help and Learning Center
γγγ«γ‘γ― (Konnichiwa), Hallo, Hola, Bonjour, OlΓ‘, Ciao!π | Global Discussions
-
Thank you, I just voted to add this feature