Hi,
I read about the solution to different % allocation to resource for same task (for example- Joe is working 20% and Cole is working 80% on the same task)
I found this post:
_____________________________
I have discovered a couple of workarounds:
- To create multiple rows for the same task and have only one party assigned to each row with their respective allocation
- Keep multiple parties assigned to the same task, then go in resource management's "Schedule" dashboard to manually delineate allocation by party for the same task
I am wondering if there are any workarounds that are less clunkier than the approaches I am currently taking. Thanks in advance for the help!
________________________
I would like to know if there is any update for this problem? and Can you please explain more about the second option?
Thanks!!!