different % allocation to resource for same task

Hi,

I read about the solution to different % allocation to resource for same task (for example- Joe is working 20% and Cole is working 80% on the same task)

I found this post:


_____________________________

I have discovered a couple of workarounds:

  1. To create multiple rows for the same task and have only one party assigned to each row with their respective allocation
  2. Keep multiple parties assigned to the same task, then go in resource management's "Schedule" dashboard to manually delineate allocation by party for the same task

I am wondering if there are any workarounds that are less clunkier than the approaches I am currently taking. Thanks in advance for the help!

________________________

I would like to know if there is any update for this problem? and Can you please explain more about the second option?


Thanks!!!