3 week look ahead including past due tasks
I created a row report from a Gannt schedule and I am I am trying to create a report that shows me the info below.
- Status is incomplete (is not equal to: Complete)
- Current Start is in the past (I need this to only be for the incomplete tasks)
- But also add tasks for the next 3 weeks.
I feel like I might be missing something in the filters to create this. Anyone have any idea what I can do to create this report to show tasks that are past due plus the tasks coming due in the next 3 weeks?
I've seen some posts mention helper columns but I don't know much about those at all. I thinking I may need a formula that basically asks if the date is past due but I'm unsure how to write that.
Here is a snippet of what I have so far but it isn't working out at all.
Answers
-
Click on that rightmost "And" to change it to "Or".
-
This "intuitive" scheduling software is maddening, at least for construction use. Unlike Procore, there doesn't seem to be any live support. Based on the cost, there should be.
Why in the world doesn't Smartsheet have a pre-built "Lookahead Template" for construction, or other sectors of business for that matter. Once we get into formulas, it's no better than Xcel.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives