Hello, i need some help how do i connect the %complete column to the status column

Younes Amine
Younes Amine ✭✭
edited 10/18/23 in Formulas and Functions

for example if the status says in progress i want the %complete column to automatically say 50%

can anyone help me?

Best Answers

  • Nick Korna
    Nick Korna ✭✭✭✭✭✭
    edited 10/18/23 Answer ✓

    You can do this with a nested IF statement, but you would need to outline what relationship you would want between the 2 columns - in your example the formula for % complete would be:

    =IF(Status@row = "In Progress", 0.5)

    The above assumes you've set the complete column to a percentage.

    However, you could set the % to give you the status instead:

    A very basic example:

    0 = Not started

    1-99 = In Progress

    100 = Completed

    This can be combined with other variables (e.g. estimated completion date) as well.

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭
    Answer ✓

    It looks like you are using dependencies. In that case you will not be able to use a formula in any column being used by the dependencies.


    You will need to flip your logic so that the Status us generated by the % Complete, and the % Complete will have to be the manual entry.


    We could also use a couple of Change Cell automations instead of a formula in the Status column to allow for manual selection of "Waiting" as needed.


    The automation would be set up to run whenever the % Complete changes to any value. You would use a condition of the % Complete being zero to output Not Started, condition of one to output Complete, and condition of greater than zero and less than one to output In Progress.

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

  • Paul Newcome
    Paul Newcome ✭✭✭✭✭✭
    Answer ✓

    Happy to help. 👍️

    Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!

    CERTIFIED SMARTSHEET PLATINUM PARTNER

    10xViz.com

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!