Hi Community,
I created a very simple automation where the trigger is when my % Complete row changes to 100% I want the Status cell value to change to complete. However it does not seem to be working. When I tried to run the workflow manually it changed all of my statuses to complete even if the % complete is less than 100%.
Tags:
Answers
-
@lisa513727 have you tried trigger when % Complete row = 1 instead of 100%?
You can also do, =IF([% Complete]@row = 1, "Complete", "Incomplete) in the status column
-
Hi @Eric Law I used the tool in the automation section where I used the dropdown to select the criteria. I will try your suggestion, thanks for much for your reply.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives