Question about resource management

Nitzan
Nitzan ✭✭
edited 11/21/23 in Resource Management

Hey Guys,

I'm trying to use resource management, but either I'm missing something or the effort calculation is wrong.

this is my demo:

Isn't the effort for Simple Demo should be:

25% for 11/20/23

75% for 11/21/23-11/23/23

50% for 11/24/23-11/25/23

150% for 11/26/23?

The weird thing is when I'm changing a random field, for example, Allocation in row 1 to 20% and then changes it back to 25%, the effort is being updated to the right one:

But when I'm refreshing the page it goes back to the first screenshot I uploaded.

Thank you for your help

Answers

  • Hi @Nitzan

    I see what you mean: the first full day is not appearing in the Panel - even when it's being recognized, you can see that it is being pulled in as the 19th, not the 20th.

    I'm unable to replicate what you're seeing:

    Here are my Project Settings, with all days set as 8 Hour Working Days

    Is it possible that your Project Settings have the 20th as a holiday?

    Cheers,

    Genevieve