Question about resource management
Hey Guys,
I'm trying to use resource management, but either I'm missing something or the effort calculation is wrong.
this is my demo:
Isn't the effort for Simple Demo should be:
25% for 11/20/23
75% for 11/21/23-11/23/23
50% for 11/24/23-11/25/23
150% for 11/26/23?
The weird thing is when I'm changing a random field, for example, Allocation in row 1 to 20% and then changes it back to 25%, the effort is being updated to the right one:
But when I'm refreshing the page it goes back to the first screenshot I uploaded.
Thank you for your help
Answers
-
Hi @Nitzan
I see what you mean: the first full day is not appearing in the Panel - even when it's being recognized, you can see that it is being pulled in as the 19th, not the 20th.
I'm unable to replicate what you're seeing:
Here are my Project Settings, with all days set as 8 Hour Working Days
Is it possible that your Project Settings have the 20th as a holiday?
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives