Copy & paste tasks and dependencies
NeuerNutzer
✭✭
Hey everyone,
i have created a template task list including their dependencies and I would like to copy and paste them in my sheet, so I don't have to figure out the dependencies for every bucket on its own. However, It appears I cannot copy and paste the dependencies :-( - is there any way of doing this in a better way or is it simply not possible?
Thanks a lot!
Tags:
Answers
-
Hi @NeuerNutzer
Have you tried using the copy automation? And make sure dependencies are turned on on your target sheet before. I know the copy automation function retains parent / children relationships so maybe it will work for this too.
I hope that helps.
Matt
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.4K Get Help
- 364 Global Discussions
- 200 Industry Talk
- 429 Announcements
- 4.4K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 128 Community Job Board
- 446 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 35 Webinars
- 7.3K Forum Archives