Would love to see reports gain functionality to display a Gantt bar based on summarized dates in a group within the report. This would facilitate my reviews with leadership by seeing the high level gantt summarized for the group (project), while also still allowing me to expand the group and see details. Thank you!
@jwoodson1191 If you are not signed up for EAP you should sign up for it. There is currently a new timeline view that may assist in this request. Become a Smartsheet Early Adopter | Smartsheet
@Samuel Mueller I actually just got EAP. Had it while at a previous company, and just got back in. Do you know where I can read some more on this timeline function in EAP?
@jwoodson1191 If you are in EAP believe you can view documentation here: EAP Track date-based work with timeline view | Smartsheet Learning Center
@Samuel Mueller yes that worked, thanks for the bread crumb!