Why is the Start Date inconsistent?
The START date on Row 813 is different in these two examples. Why?
The image labeled "Correct" has Row 813's predecessor pointing to a row that has no predecessor. As such, Row 813's START date is one day later than the FINISH date of its predecessor. The date on Row 813 shows (3/12/24 shown in yellow). This seems correct.
The image labeled "Wrong" shows its START date as 3/11/24, which seems wrong.
Why does this happen? Both examples point to a row that FINISHES on 3/11/24 (shown in yellow). Why does one situation have the START date as 3/12 and the other 3/11? Why?
Answers
-
It is impossible to say why that is showing incorrectly without seeing how the date is being generated. Since it is working in one of the sheets I would recommend comparing the formula on the sheet where it is functioning correctly and fixing the formula that is not working to match. If you can't find it you can reply here with the formula and we can potentially help guide you in the right direction.
Best,
Zach Hall
Training Delivery Manager / Charter Communications
-
Thanks for the comments, Zachary. There are no formulas in this sheet. It's simply Start/Finish dates, Predecessors, and Durations... and, the dates are being controlled by the sheet's Dependency Settings. This is all pretty standard stuff.
Also, the odd behavior will occur in the same sheet if you alter the predecessors as shown in the screen-grabs.
It's as if this issue is part of the Smartsheet platform itself. It's repeatable. It's not a result of any other factor, including the formulas because, again, formulas are not being used.
Thanks again for your comment. If you think of something else, please pass it along.
-
Hi @Matt Haas
When Dependencies are enabled, there is a hidden time associated with dates to identify if the date is the start of the day or the end of the day - this enables the FF, FS, SS, and SF Predecessor links to be created.
Without seeing how all of your tasks are connected, my guess here is that row 811 has a time value that starts the day instead of ends the day (this may be due to its predecessor links).
To test this, add a Text/Number column to your sheet and use the simple formula:
=Finish@row + ""
This will show you the hidden time value and explain why some tasks start on the same day and some start on the next day.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives