Pull milestones from multiple projects into single sheet
Hey all!
I'm managing multiple medium-large scale projects within my org, all on their own project plans, and I'm wanting to build a consolidated enterprise-wide tracker so I can see where I'm at with all my milestones in a single plan / dashboard.
Is there a way / template that would allow me to pull in milestones from multiple projects into a single Smartsheet?
Thanks!
Tags:
Answers
-
Have you looked at row reports? You can select multiple sheets and any common columns from them, to display in one place. You can then view the report as is, or create a dashboard and embed the report into it.
https://help.smartsheet.com/articles/2482078-build-a-row-report-with-report-builder
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 376 Global Discussions
- 205 Industry Talk
- 437 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives