How do you run schedule so it shows progress?
I am placing % complete and it's not running schedule
Answers
-
Are you talking about visualizing the % complete on the Gantt (red). If you right click any column header, or if you are in Gantt, select the Project Settings (green), and then you can select which column to use to show % complete.
If you're talking about rolling weighted % complete up to a parent row, you must select "dependencies enabled" in the project settings window. FYI if you do this, it does to weighted averages based upon the task durations, as below.
Jason Tarpinian - Sevan Technology
Smartsheet Aligned Partner
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 376 Global Discussions
- 205 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives