How do you run schedule so it shows progress?
I am placing % complete and it's not running schedule
Answers
-
Are you talking about visualizing the % complete on the Gantt (red). If you right click any column header, or if you are in Gantt, select the Project Settings (green), and then you can select which column to use to show % complete.
If you're talking about rolling weighted % complete up to a parent row, you must select "dependencies enabled" in the project settings window. FYI if you do this, it does to weighted averages based upon the task durations, as below.
Jason Tarpinian - Sevan Technology
Smartsheet Aligned Partner
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 394 Global Discussions
- 213 Industry Talk
- 449 Announcements
- 4.6K Ideas & Feature Requests
- 141 Brandfolder
- 132 Just for fun
- 131 Community Job Board
- 453 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives