Summary path
Hello,
Is there a way to reflect gaps in the summary path as i want to see when there are no deliverables within a certain timeframe for resource management. The project spans over many years so the summary path appears as though there are continuous deliveries when the subtasks field is minimised which is now the case.
Thanks.
Answers
-
Hey @Megan.elh
By "summary path" do you mean the headers? I don't believe there's a way to reflect those gaps, but it's an interesting idea. I'm sure the Product team would like to hear your feedback (with screen capture examples if possible), so when you have a minute, please submit your feature request by creating an Idea Post in the Smartsheet Product Feedback and Ideas topic here in the Community.
Cheers,
Genevieve
-
Hi Genevieve,
I've attached an image which will hopefully help. If you dont believe it's currently possible to reflect the gaps (as you can see the next delivery isn't in the selected screenshot) i'm happy to share my suggestion/feedback with the product team. Appreciate your assistance.
Thanks.
Regards,
Megan
-
Hi @Megan.elh
Thanks for clarifying you're talking about Parent Row task bars in a Gantt View in Smartsheet (versus a visualization in Resource Management).
Yes, this is correct. There is no current want to display gaps in the Parent Row's task bar. Please feel free to add your vote and voice to these related Product Ideas:
- Gantt Bar with milestone
- Allow multiple task dates within the same row have different colors
- Single Row Timeline
Cheers,
Genevieve
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.1K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 444 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 450 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 290 Events
- 35 Webinars
- 7.3K Forum Archives