hello,
I am having same issues.. i am using Smartsheet for tracking activities on building a machine from scratch. We have about 5000 activities and a lot of them subdivided in 4 or even 5 levels. Whenever I add (insert) a new activity all activities below are not connected anymore via predecessors row. A nightmare!
Is there any solution already? We are in Q2 2024….
-
Hi @Sonet
Can you provide some screenshots for your situation?
Gia Thinh Technology Co., LTD - Smartsheet Solution Partner.