RAG Status

pjb
pjb ✭✭
edited 05/09/24 in Formulas and Functions

Hello! Newbie here :)

I was wondering if someone could help with a formula I'm attempting to put together to calculate a RAG symbol status for individual tasks as well as the overall project plan.

Individual Tasks:
If status is complete = blue
If status is in progress OR not started AND end date is today = yellow
If status is in progress OR not started AND end date is in the past = red
If status is not started AND start date is in the past = red
If status is in progress AND end date is in the future = green
=IF(Status@row = "Complete", "Blue", IF(AND(Status@row = "In Progress", [End Date]@row <= TODAY()), "Yellow", IF(AND(Status@row = "In Progress", [End Date]@row < TODAY()), "Red", IF(AND(Status@row = "In Progress", [End Date]@row >= TODAY()), "Green", ""))))

Overall Project: calculates the overall status of the project based on the above.

Thanks in advance!

Best Answer

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!