Is there a way to set a time between milestones or tasks?

I have a committee meeting which is a milestone.
If certain documents need to be submitted 2 weeks before that meeting, how do I set that up in SmartSheet?
I thought of just making a 2-week task called something like 'secretary prepares agenda', but it feels a bit clunky.
Answers
-
OK lets say the agenda was row one and the meeting was row two. The predecessor you want in row one is 2SF-10
Explanation:
Smartsheets has 4 different types of predecessors
FS: When the predecessors finishes the successor starts. i.e. 2
SF: When the predecessors starts the successor finishes. i.e. 2SF
SS: When the predecessors starts the successor also starts. i.e. 2SS
FF: When the predecessors finishes the successor also finishes. i.e. 2FF
You can add lags between tasks by adding +{No of Days} after the predecessor syntax i.e 2+10
You can add leads between tasks by adding -{No of Days} after the predecessor syntax i.e 2-10
You have a Start-Finish predecessor with a 10 day lead, therefore 2SF-10.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 205 Use Cases
- 516 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 82 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives