I have a number of project plans where someone has completed a task early. For example, we estimated a Technical Consultant would take 6 weeks to meet with various teams. He completed the task in 4 weeks and marked the task complete. The task now shows in the Capacity Plan for the next two weeks, showing that he has no availability.
How are people managing this? Are they going back into each task in the project plan and amending the end date?
Similarly, I completed a task on a project yesterday. It was planned for next week but I had time spare. It's still showing that I need to complete it next Tuesday. I don't want to change too much because the dependant tasks, are planned for Wednesday and Thursday.
Any thoughts on how to manage this quickly and efficiently?