Hello,
How do I disconnect a resource sheet from Resource Management?
Answers
-
In the screenshot you've shown, you're not currently connected. Just press the X and you should be OK.
When you are connected, going into that panel gives you an option to disconnect. Be careful though, when you disconnect a project, the associated project in Resource Management automatically archives itself. That caught us out several times.