Show multiple resources for one task.
I'm not using the separate Resource Management module, but the one included in the Business plan.
We shift workers around a lot. If I have two or more resources in the "Allocated To" column, and one of them leaves the project before the other, how do I show this?
Say one of the workers will stay until completion but the other has to leave early due to a personal matter or has vacation. If they both have the same allocation % assigned to them, I'm not going to see that one will be leaving early and then I'll end up understaffed on the project.
How can I show multiple allocated resources (Assigned To) separately?
TIA
Answers
-
You'll have to split the work up onto 2 tasks, each assigned to 1 person, in order to see differences in allocation and dates.
-
@Brian_Richardson That is unfortunate. Some of our projects have 10+ people working on them. The schedule is going to get messy.
I am doing a demo of Resource Manager and was told it has the capability to do more with this than the included tracker. Do you have any experience with this?
Thanks.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives