Smartsheet Calendar/Outlook event shows "busy"
I am working on integrating a smartsheet calendar view into an outlook calendar. The appts show as busy (thus coloring out the whole day). Is there a way to change that?
Answers
-
Hi @Mer.!
When integrating a Smartsheet calendar view into an Outlook calendar, keep in mind that tasks can't be scheduled at a specific time, only on a certain date. Project sheet tasks, even those with partial-day durations (like hours or minutes), will still appear as spanning across full days in the Calendar View and any published versions.
For more details, you can refer to this section "Select dates to display" in the article Work with Calendar View.
If you'd like to submit a feature request to the Product team, feel free to do so through the Smartsheet Product Feedback and Ideas section in the Community: Smartsheet Product Feedback & Ideas.
I hope this helps!
Cheers,
Isaac.Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 413 Global Discussions
- 221 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 461 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives