Hi all,
I am managing a project portfolio and need to look at resource capacity impact for future projects. Its likely there will be a number of scenarios, based on project prioritisation and resource availability through the year.
I had intended to use the Resource management People view to look at resource loads and use filters to see how the load changed when project were included or not, but have been advised by Smartsheet Support that the resource load % are not recalculated when you change filters.
How are you doing capacity management scenario management? Is the only way to change start and end dates for each project?
Thanks
Simon