One of my clients uses Hammock Tasks to represent Project Management and Organizational Change Management in their projects.
A Hammock Task is one whose Start and Finish dates are driven by different Milestones. The Start Date would be the date of one Milestone and the Finish Date would be the date of a subsequent Milestone. For example the "Organizational Change Management" task would have a Start Date of the "System Design" milestone and a Finish Date of the "Handover to Operations" milestone.
In other Project Management tools, I could link the date cell from the relevant Milestones, but it doesn't look like I can do it in Smartsheet. How can I make the Start Date for a task dependent on one Milestone and the End Date for the same task dependent on another Milestone, thereby creating a Hammock Task?