Independent work days for tasks or resources?
I have holidays blocked out in my calendar, however there are certain tasks/resources where the holidays don't apply. For instance, China is closed for all of February for Chinese New Year and I have those dates blacked out, but I don't want them to apply for folks in USA who will still be working. Is there a way to either apply holidays for specific resources or a way to make certain tasks override the calendar?
Comments
-
Hello Kroll,
Non-working days apply to the whole sheet, however, you can used Elapsed Time to make a task ignore non-working time.
Elapsed time (lead with an e to indicate duration in elapsed time e.g. e3d, e5h, e3.5d, etc). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet.
For more information, see https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#Duration
Thanks!
Schiff
Smartsheet Support
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives