Sign in to join the conversation:
So with the new referencing sheets feature (at least I think it's new) is it possible to have one sheet that would be the master for all summaries and metric information rather than roll them up into extra rows at the top of each sheet?
Yes.
That is one of the benefits of cross sheet referencing.
Craig
Hello Community, Looking for some help today to figure out how to correct time zone differences with dates. I have set up an Automation workflow to remove future dates in schedules and send notifications to the PMs. This would prevent future dates being collected in reports and dashboards. The settings for the Owner…
I have written an automation that moves content from one sheet to another when certain criteria are met. I thought the cell history came across with the row but when I click on "View Cell History" after it is moved, I only get the history for the move and nothing prior. Is this working as designed?
How do I get a row on a Gantt chart to show the earliest date from amongst a set of predecessors? I have a gantt chart where I want one row to display a 0-duration task with the earliest start date from amongst five predecessors. I've entered them as start-to-start predecessors, so in theory it should start when the…