So with the new referencing sheets feature (at least I think it's new) is it possible to have one sheet that would be the master for all summaries and metric information rather than roll them up into extra rows at the top of each sheet?
Yes.
That is one of the benefits of cross sheet referencing.
Craig
Hi there. I am working on several sheets that have a column called "Hours" which holds an hour estimate for task rows. I'd like for their parent rows to have a sum like "=sum(children())" so I can see how many hours are estimated for each project. My problem is that while I can manually set this for the rows, these sheets…
I am struggling finding a formula to mark the successor task "In Progress" when predecessor is "Complete" like can be done in MPP. I am encouraging my organization to move to SS with the automation, reporting, dashboard and automation capabilities, and away from MPPP so trying to replicate some of the items they utilize in…
HI All, I have a formula that i have got working - only issue i have is I have run out of cross reference "space" and cannot add my last spring to complete my function is there anther way to do this Source sheet OR date UP date Site Target sheet Required date Updated Date Site i need to return source sheet UP date, when OR…