I want to track how long an open task is delayed on a project
Hello,
You might be interested in using the baseline method to track planned vs actuals: https://www.smartsheet.com/blog/quick-guide-mimicking-baseline-functionality-smartsheet
Hi,
By how long you mean:
How much diff there was from the initial due date?
or
If a task is not completed, how much time past from the due date (meaning Today - Due date)?
How long has past since a task is considered delayed (time that past since status was changed to "delayed", etc.)?
or, something else?
Sorry, I was out of the office. I would like to track: If a task is not completed, how much time has past from due date and also track due date changes (the difference between the original due date and new due date) open task only.
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…