I want to track how long an open task is delayed on a project
Hello,
You might be interested in using the baseline method to track planned vs actuals: https://www.smartsheet.com/blog/quick-guide-mimicking-baseline-functionality-smartsheet
Hi,
By how long you mean:
How much diff there was from the initial due date?
or
If a task is not completed, how much time past from the due date (meaning Today - Due date)?
How long has past since a task is considered delayed (time that past since status was changed to "delayed", etc.)?
or, something else?
Sorry, I was out of the office. I would like to track: If a task is not completed, how much time has past from due date and also track due date changes (the difference between the original due date and new due date) open task only.
Hello, I have a destination sheet that is cell linked to a source sheet. The source sheet is constantly being updated (adding information, deleting information) but the destination sheet does not reflect those updates. Is there any work around this issue? Any way that the destination sheet reflects the updates real time? I…
Hi Can you utilize forms to make data entry easier into a row that already exists?. For instance, if I have pre-populated a sheet with 100 rows/items can I use a form to update certain columns in these rows…to make columns with multiple lines of text easier to enter? Many thanks Matt
i got this error while working , when i close it it pops up again, i even restarted the app but no use. this happened last week to but it stoppedthe next day. can summon help . Update : it now stopped, after restarting it again and popping up again it stopped.What is triggering this error .