Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Subtask Dependencies Error Message "REF"
I am getting a "REF" message in the subtask cell for Predecessor column.
For example:
Line 3 Start SF, start date: 8/18/15; end date: 8/18/15 = I entered the number 2
Line 4 Update SF, start date: 8/19/15; end date:9/17/15 = I entered the number 3
Line 5 Review SF, start date: 8/19/15; end date: 9/16/15 = I entered the number 4 and I get the "REF" error message
Line 5 is where I am having the issue and I do not understand. Please assist, thanks.
Comments
-
Is line 4 a Parent Row? That would cause a #REF error. A predecessor needs to be a row with no children.
-
Christina, could you show us a screenshot of your sheet and point out where you are getting this error?
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 379 Global Discussions
- 210 Industry Talk
- 441 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 300 Events
- 33 Webinars
- 7.3K Forum Archives