2 week task for 2 hours each day
Nancy
✭
Is it possible to have a task with a duration of say 2 weeks, but only allocate a fraction of the day’s hours to the assigned resource?
For example, John Smith is assigned Qlik development that will last for 2 weeks, but will only be developing for 2 hours/day.
I know it’s possible to change the default length of a day from 8 hours to something else (link here), but that is not really helpful if some resources are devoted all day to a task whereas others are multitasking.
Comments
-
You may achieve that by splitting entire task for subtasks (days in this case) and apply 2h Durations for each day.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives