holiday period
Hello,
I'm trying to add holiday (complete shut down for 2 weeks) period to my project sheet. I've done it in project settings ect. but it is not showing on my sheet. The project should be that much longer and I was expecting to have a separate bar to appear showing holiday period cutting all tasks started and putting them on hold for that period but this didn't happen. Can anyone help me with thit please?
Many thanks, Gabor
Comments
-
Hi Gabor,
Holidays appear in the Gantt chart as a light pink vertical strip—tasks can be scheduled to start on holidays, but can't be scheduled to end on them.
Holidays won't split or change formatting of the Gantt bars for your tasks; instead the Gantt bars will automatically push out end dates to the next available working day.
The duration column will only count working days (won't count holidays or non-working days).
More info on holidays is available in the help center: https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
There currently isn't a way to show custom formatting on the Gantt bars themselves (different color, split task line, etc.) but when you have a moment, please submit a Product Enhancement Request using the form under Quick links on the right of the Community site and let our Product team know that you'd like to see this added.
-
Hi Shaine,
Thank you very much for your response! I've put away the programme and only started working on it again now we actually started the project so I only saw your reply now.
I'm still struggling with the same issue though. I've put in the dates of the holidays (within settings, working days) but it does not appear any different on the sheet (not pink). I'm probably doing something wrong but can't really figure out what.
Would appreciate your help again!
Thanks,
Gabor
-
Hi,
I have the same issue, I've configured the holidays (in account settings) but the days are not skipped. I'm new at smartsheet (actually, I'm testing the tool) so, maybe I'm doing something wrong. Can anyone help me? Thanks in advance
Doris
-
Dear Doris, Shine and Gabor,
I guess, it is a misunderstanding.
I have several workers and they have in different time (from a few days up to several weeks), divided over a year holiday.
It is possible, that one of them works on a large project and only his work on this this project must be interrupted for his holiday.
So I can't set this time as a general holiday, but it is not for the other workers.
Further, I need to see in advance on an overview on which days in a year is he not available.
Who can help me?Thanks in advance.
Laszlo
-
Hello—
Try using the Team Vacation Planner template in Smartsheet: https://www.smartsheet.com/solutions/team-vacation-planner
With this template, you'll be able to set and plan vacation for your workers (resources).
You might even use this template with Resource Management so that when you assign them to tasks in other sheets (that also have Resource Management enabled), you'll receive an Overallocated badge icon directly in the sheet. More on this functionality here: https://help.smartsheet.com/learning-track/smartsheet-advanced/resource-management
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives