I would like to create a milestone where it is within a timeframe I decide to setup. For Example if I put the Start Date as 5/15/18 and a target date of 5/23/18 how can I go about doing this so we can see a milestone.
Milestones are created by using 0 in the duration and having a start date.
https://help.smartsheet.com/articles/516406-creating-a-milestone
Hi Justin,
Further to Mike's solution, you could link the milestone to your task using the Predecessors column. This way your Milestone would shift when the Finish (Target) date is updated.
Kind regards,
Chris McKay
Thank you for the information
Thank you for the follow up information
Great suggestion Chris. I hate it when the tasks move but the milestones don't.
I have a workspace that I created with two subfolders. A user needs to have access to only one of them but when I have that folder selected, I can only share the entire workspace with them. Is there a secret way that I can share the parent folder and ensure that any new files created will be shared with the same people? I…
I have a Pro plan but I cannot create ANY reports. The system does not allow me to choose a folder, and consequently a sheet to create a row report and suggests an upgrade to Business or Enterprise. I'm quite new to Smartsheet and feel a bit disappointed with this limitation, or maybe I'm just doing something wrong. Alberto
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…