Does Smartsheet have the ability to move rows to a new sheet based on a condition being completed? An example would be if you have multiple projects (rows) on one sheet and want them to be moved to a new sheet when the status is changed to complete. Is that possible?
Hi,
This is something that I would like to do on a few of my Sheets. Is it possible?
Unfortunately there is no way to automate this. The closest you can get is to create a report, but all that will do is summarize the Completed tasks. It will not move them from the original sheet.
Depending on the details this is probably possible to set up with the help of Zapier or another similar service.
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.