Task not scheduling properly

Options
cread
cread ✭✭
edited 12/09/19 in Smartsheet Basics

I have a plan in a smartsheet which isn't scheduling as expected. several task that have no predecessor seem to be staying put. I'd expect them to move to theΒ project start date.

I can find no option to change constraint type.

I've exported it to MS Project and it exhibits the same behaviourΒ until I reviewΒ the Resource sheet and delete all its contents, then it schedules correctly. I'm unsure where to find this info in smartsheets. See attachment.

How do I ensure the plan in smartsheets schedules correctly?

Picture12.png

Comments