Sign in to join the conversation:
I want to have a condition where IF Delivered column checkbox is checked, then that whole row will be deleted. Is that feasible?
Can you please guide me how to start with it?
Hi, this would be really helpful - but not to delete the row, just to hide it please. Not sure it's possible, but...
There are a couple of ways this might be possible. If you set up a default filter on a sheet to always load rows where complete box is unchecked, then, if you checked off a task or two and reloaded the sheet those tasks would not be visible the next time it loads.
To do this:
See attached screenshot. (Right-click on the image and view in tab.
If you wanted to delete the row, you should look at Craig Williams' post on using Zapier. http://ronin-global.com/2016/12/11/smartsheet-fixed-date-upon-completion/ -- Though the post is about setting a specific date, you can use the same functionality to delete rows. It would require a paid plan for Zapier but it is possible with this tool.
Hi, I cannot see your screenshot. What was your recommendation?
This is great! Thank you so much. I have added a new filter called "Delivered"
Glad I could be of assistance. Hope its working well for you.
I'm having an issue with this sheet: Smartsheet - Quote The COST / PC column is where the issue is happening. On line 4, I'm testing out using a different material that doesn't conform exactly to the sheet's setup but I'm trying to build in functionality to make it possible. When the columns being added by COST / PC are…
I need this formula to sum cells in a reference sheet based on dates. The reference sheet has a column with dates, and there could be multiple of the same date. I was able to get this formula to work on the top line in the screenshot, but the next line is adding the 2 week ending sums together. The planned bushels for week…
I am looking for your help once again :) So the below formula works fine for me however I have other sheets that I also need to reference. I'm assuming I would need to add an AND or OR formula to the below however I'm not sure where or what structure the formula should be. And its to reference another 4 sheets, including…