Sign in to join the conversation:
I am working on a project sheet and the day my first task ends, my second task starts. Is there a way to make my tasks start day the same as its predecessors end date?
Thanks!
Enable Dependencies
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
In the [Predecessor] column, second task row, enter the row number of the first task.
The default dependency is FS (finish to start)
Craig
Thanks for the help! I have done what you recommended and the start day does not become the same as the end day.
Ah, sorry, there's a nuance that might not be explained in the link I provided. It has been a while since I read it.
Your first task starts at 8am on July 10th and ends at 5pm on July 25th, unless you have changed your working day in Project Settings.
The next task starts immediately after that, but the PM tool thinks everyone went home and so it starts on the next working day. If July 25th was a Friday, it would start on Monday if you had not changed the settings, but it appears you did since your duration is 16d.
Depending on how accurate the 16d is, if you are using it to determine expected costs, and other factors, it can get tricky to show what you want.
You could provide a lead on the 2nd task in the Predecessor column
=18 - x
where x could. be 1d, 1h, 1m
but those throw off the rest of the dates too.
You could shorten the duration of the 1st task, say to 15.5h
If I were PM, I would likely let the handler of the first task know "I need this before noon on the 25th because Nancy needs to do her thing and we can send it to the customer by COB"
I hope this helps.
Thank you. Shortening the duration of the task, to a ".5" works. So if you need to do Task 1 that has a 2d duration, before Task 2 - and want task 2 to begin the same day - You can shorten the Task 1 duration to 1.5 and that fixes the issue
I made a mistake and end up deleting information from one of my sheets, but now I cannot find a way to recover a previous version of this sheet to recover my original file. I need help to fix this, and it seems Smartsheet is really lacking this recovery feature for everything I'm reading and checking online. Any help or…
Has anyone figured out a way to use a column as a created date but not have the time stamp? It causes problems for my manager trying to use that date to pull into PBI. I know how to convert in a helper column to a year-month and a year, but those have to be text/number columns, not date columns and he can't use those…
I am looking for a way to automate a cell so that when column A displays 9 'Days Open' (or between the values 0-14) the 'Req Age' will auto populate (or trigger) the ranges provided. Image below: I want the highlighted section to auto populate based on the value in 'Days Open'