Sign in to join the conversation:
I am working on a project sheet and the day my first task ends, my second task starts. Is there a way to make my tasks start day the same as its predecessors end date?
Thanks!
Enable Dependencies
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
In the [Predecessor] column, second task row, enter the row number of the first task.
The default dependency is FS (finish to start)
Craig
Thanks for the help! I have done what you recommended and the start day does not become the same as the end day.
Ah, sorry, there's a nuance that might not be explained in the link I provided. It has been a while since I read it.
Your first task starts at 8am on July 10th and ends at 5pm on July 25th, unless you have changed your working day in Project Settings.
The next task starts immediately after that, but the PM tool thinks everyone went home and so it starts on the next working day. If July 25th was a Friday, it would start on Monday if you had not changed the settings, but it appears you did since your duration is 16d.
Depending on how accurate the 16d is, if you are using it to determine expected costs, and other factors, it can get tricky to show what you want.
You could provide a lead on the 2nd task in the Predecessor column
=18 - x
where x could. be 1d, 1h, 1m
but those throw off the rest of the dates too.
You could shorten the duration of the 1st task, say to 15.5h
If I were PM, I would likely let the handler of the first task know "I need this before noon on the 25th because Nancy needs to do her thing and we can send it to the customer by COB"
I hope this helps.
Thank you. Shortening the duration of the task, to a ".5" works. So if you need to do Task 1 that has a 2d duration, before Task 2 - and want task 2 to begin the same day - You can shorten the Task 1 duration to 1.5 and that fixes the issue
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…