Sign in to join the conversation:
I am working on a project sheet and the day my first task ends, my second task starts. Is there a way to make my tasks start day the same as its predecessors end date?
Thanks!
Enable Dependencies
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
In the [Predecessor] column, second task row, enter the row number of the first task.
The default dependency is FS (finish to start)
Craig
Thanks for the help! I have done what you recommended and the start day does not become the same as the end day.
Ah, sorry, there's a nuance that might not be explained in the link I provided. It has been a while since I read it.
Your first task starts at 8am on July 10th and ends at 5pm on July 25th, unless you have changed your working day in Project Settings.
The next task starts immediately after that, but the PM tool thinks everyone went home and so it starts on the next working day. If July 25th was a Friday, it would start on Monday if you had not changed the settings, but it appears you did since your duration is 16d.
Depending on how accurate the 16d is, if you are using it to determine expected costs, and other factors, it can get tricky to show what you want.
You could provide a lead on the 2nd task in the Predecessor column
=18 - x
where x could. be 1d, 1h, 1m
but those throw off the rest of the dates too.
You could shorten the duration of the 1st task, say to 15.5h
If I were PM, I would likely let the handler of the first task know "I need this before noon on the 25th because Nancy needs to do her thing and we can send it to the customer by COB"
I hope this helps.
Thank you. Shortening the duration of the task, to a ".5" works. So if you need to do Task 1 that has a 2d duration, before Task 2 - and want task 2 to begin the same day - You can shorten the Task 1 duration to 1.5 and that fixes the issue
Hi Everyone, I created some forms for our powdercoat test logs. The forms are working great for the employees to input the data. The problem I am having is with giving the supervisors and managers access to the sheet. I gave them Editor Cannot Share permissions to see and edit the sheet. But they are saying that Smartsheet…
I have a grid with two forms: one in English and one in German. The dropdown questions are working fine, but the answer options always appear in English. When I try to change the options to German, Smartsheet automatically updates the answers in the English form as well. I’ve tested this several times, and every time I…
I had data deleted from a column in a tracking sheet. (2K+ rows) I pulled a snapshot from the activity log and I want to pull back the data from just the one column. I was told the right process was under File>Import>Update Rows, but I don't have that option under import. Is there another way to do this?