I am working on a project sheet and the day my first task ends, my second task starts. Is there a way to make my tasks start day the same as its predecessors end date?
Thanks!
Enable Dependencies
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
In the [Predecessor] column, second task row, enter the row number of the first task.
The default dependency is FS (finish to start)
Craig
Thanks for the help! I have done what you recommended and the start day does not become the same as the end day.
Ah, sorry, there's a nuance that might not be explained in the link I provided. It has been a while since I read it.
Your first task starts at 8am on July 10th and ends at 5pm on July 25th, unless you have changed your working day in Project Settings.
The next task starts immediately after that, but the PM tool thinks everyone went home and so it starts on the next working day. If July 25th was a Friday, it would start on Monday if you had not changed the settings, but it appears you did since your duration is 16d.
Depending on how accurate the 16d is, if you are using it to determine expected costs, and other factors, it can get tricky to show what you want.
You could provide a lead on the 2nd task in the Predecessor column
=18 - x
where x could. be 1d, 1h, 1m
but those throw off the rest of the dates too.
You could shorten the duration of the 1st task, say to 15.5h
If I were PM, I would likely let the handler of the first task know "I need this before noon on the 25th because Nancy needs to do her thing and we can send it to the customer by COB"
I hope this helps.
Thank you. Shortening the duration of the task, to a ".5" works. So if you need to do Task 1 that has a 2d duration, before Task 2 - and want task 2 to begin the same day - You can shorten the Task 1 duration to 1.5 and that fixes the issue
I have a workspace that I created with two subfolders. A user needs to have access to only one of them but when I have that folder selected, I can only share the entire workspace with them. Is there a secret way that I can share the parent folder and ensure that any new files created will be shared with the same people? I…
I have a Pro plan but I cannot create ANY reports. The system does not allow me to choose a folder, and consequently a sheet to create a row report and suggests an upgrade to Business or Enterprise. I'm quite new to Smartsheet and feel a bit disappointed with this limitation, or maybe I'm just doing something wrong. Alberto
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…