Allocation meeple appearing without any concurrent task
Hi,
I got a mysterious meeple over-allocation icon that I have check numerous times did not any have a concurrent task. As I interpret the allocation icon, it means I am doing many task as the same time on which numerous occasion I can clear it by changing the schedule or dividing the task to subtask or phases with different start date and end date that will not conflict other task. I also assign to another person if I am overallocated,
I also made the task to have 0.125d duration and it dose clear the over-allocation meeple
What cause this? Is this a bug?
Thanks
D Micu
Comments
-
Hi D Micu,
It sounds like you're set to 100% allocation on more than one task at the same time—either on the same sheet or across multiple sheets. Smartsheet recognizes you as being overallocated because of this. I'd recommend reducing your % allocation on all of your tasks that run concurrently, or changing the start/finish dates on your tasks so they don't overlap as much.
More information on resource management is available in our help center: https://help.smartsheet.com/articles/1346969-resource-management-allocation-team-enterprise-only-
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 304 Events
- 34 Webinars
- 7.3K Forum Archives