I'd like to have an alert on a date column, so that 30 days prior to that date we are notified.
Is this possible?
Thanks,
Brendon
Hi Brendon,
You can set this up in the "Alerts & Actions" menu --> "Set a reminder", but there are only settings for max 14 days before so what I usually do is that I add a column that specifies how many days before that I want the reminder to trigger and then in the date column I add a formula like the one below. Keep in mind that this will count all days.
=[Date Column]@row - [Days before reminder Column]@row
More info: https://help.smartsheet.com/articles/542913-using-reminders
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant @ Get Done
I learned something (kia ora)
Craig
Ngā mihi nui Andrée,
Trying your solution, I must be doing something wrong? I have tried without the brackets, and also tried 'Reminder Date' as a text field and a date field. (Exp is a date field)
Screenshot here
goo.gl/QgVW1f
Your link does not work.
It may not be clear, but Andrée's solution:
=[Date Column]@row - [Days before reminder]@row
requires TWO new columns. One that houses the Date (a Date type column, used in the Alert) and the [Days before reminder] which is a Text/Number type column with the number of days (30 in your stated case)
This is (I assume) for flexibility if some tasks are 30 days, some 45 and so on.
You could also change the formula to
=[Date Column]@row - 30
and skip the second column entirely.
Maybe that helps? I had to reread his answer to get that too.
Did you get it working?
Andrée
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…