Hi, I'm using rows linking when one task is needed for different projects. The Allocation % field is linked as well in such situation. The problem is that Smartsheet treats linked allocations as two different tasks and adds allocations, instead of reading Allocation % only from the master sheet.
Do you have a solution how to link allocations in this case?
Torn off Resource Allocation feature in one sheet is not an option.
Example:
Project 1: Task 1 - Assigedn for John - from 18.05 - till 19.05 - Allocated 30%
the same task is a step for another projects, so I link the row.
Project 2: Task 1 - Assigedn for John - from 18.05 - till 19.05 - Allocated 30%
And I expect smartsheet to show is Resource viewer only 30% for John, not 60%.