I do not want weekends to display on the Calendar view of a task list, but I don't see any way to do this in the properties. How is this accomplished?
Hi Troy,
Unfortunately, there isn't a way to do it in the native Calendar view. The good news is that it's possible with the Add-on - Calendar Application by Smartsheet.
Please see the attached link/screenshot for more information.
Calendar Application by Smartsheet
I hope this helps you!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I created a new sheet for my team by replicating an older sheet and now my tasks aren't pulling into my task report or any of my teammates. I confirmed the sheet was selected in my report but it still isn't pulling in. I've never had an issue with this before so would love some advice on troubleshooting.
Can someone help me and give me an idea on how to create a cost estimate for installations, with a total for each chapter by groups, subgroups and types of work, but at the bottom of each chapter. https://us.v-cdn.net/6031209/uploads/0OSH46KSC2LH/cost-estimate.xlsx Thanks
Hi Everyone, I created some forms for our powdercoat test logs. The forms are working great for the employees to input the data. The problem I am having is with giving the supervisors and managers access to the sheet. I gave them Editor Cannot Share permissions to see and edit the sheet. But they are saying that Smartsheet…