I have a task for a project that should be completed on Friday. The following Monday, I have a milestone (meeting) to review that task (proposal),
The completion of the task on Friday is the predecessor for the milestone on Monday, but as soon as I set that predecessor, the milestone is moved to Friday too.
I can't figure out how to make this represent the actual timeline of events.