% complete based on count of completed pieces
Options
AndyO
✭
Hi,
I'm running a project where I want to report our the % completion of a sub task based on the # of pieces completed. I'm thinking I need to create a formula as the % of completion functionality looks at duration vs. actual amount of work completed. Can someone offer guidance?
Comments
-
Have you tried
=AVG(CHILDREN())
?
Help Article Resources
Categories
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!