Hi - I'd like to create a recurring milestone in a gantt chart. Do I need to create multiple activities on the list view or is there a formula that will generate a recurrence for a single activity?
Thanks!
Hi BBrooks,
Thanks for posting. We don't currently have a way to create recurring tasks or milestones so the best approach would be to create a series of milestones. You could create a dependency with lag so that all of your milestones are a week apart, or two weeks apart or whatever you recurrance is. That will allow you to move the entire block as one group.
Hope that helps,
Robin