Within a team of 13 users in Smartsheet, we are struggling with the resource management and allocation of tasks. If I want to allocate a task to a staff member which will require 30% of his or her time over a period of 2 months (but without knowing when he or she will work on this precisely), how can I do that ?
Also, if I change the starting date of an activity, it automatically changes the end date. How can I change it, so that the duration changes and not the end date ?
Don't know if that makes sense ...