Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Burn down
Comments
-
Kate,
If I understand your question, I keep the financial data and the non-financial data separate from each other. The non-financial data goes into a workspace or set of sheets shared to the users and the financial data goes somewhere else with different persons shared to it.
I use sheet cell linking to connect the data, usually with sum rows for hours by person, for example.
Hope that helps.
Craig
-
Is there a burn rate template?
In a given project we have estimated and actual hours for each task/phase and an associated estimated cost for each task based on number of projected hours for each resource. Each resource has different hourly rates. I want a sheet that would tell me where we are at in terms of pricing for each task and overall compated to the estimated project cost.
-
I too would be interested in a Burn rate template if anyone is interested in sharing.
Regards
-
Kegan or Kate,
Can you provide a reference to what you mean when you say Burn Rate?
I have conflicting information and want to investigate this.
Thanks.
Craig
-
Im also interested in this, as it could give historics and velocity of repeated tasks and would help with estimating future projects. On that note does the smartsheet team have an estimating platform?
-
Brian,
Oh, how cool would velocities be?! Anything to help people improve their estimates is helpful.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives