Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Getting RowID in a sheet?
Is there a way to get the rowid for a different row for a comment.
I have a schedule with a delay of 3d because of something external to the project.
In the Predecesor column I have 23FS+3d because of the delay after completing the task on row 23.
I would like a comment
="This is delayed because of (reason) after completion of " + RowID(23)
and then if row 23 changes (because I add three rows above it, for example, formula will change with it. I could of course reference the task text directly. But I like numbers for the self-referencing aspect.
Thanks.
Craig
Comments
-
Craig, rather than getting a RowID, you could reference the predecessor value which would change if the predecessor row moves.
For example:
="This task is delayed because of row " + Predecessors11
Would show:
This task is delayed because of row 9
Then, if you move row 9, the predecessor will update and in turn, this formula will update with the new row number.
-
Brilliant.
Thanks Travis!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 495 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives