Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Fixed duration in the Gantt chart
Hi all,
I'm evaluating duration time of every tasks. In the sheet, I set a duration time, a start date and the end date is adjusted accordly. If I want to change the start date, the end date will be updated and vice-versa. It's fine.
However, in the Gantt chart, when I'm touch a gantt bar to change the task start, it's really easy that I will change the task duration in opposite of the task start/end time, that is what I want. It's a trouble, because the duration was calculated after a specification of the task and an evaluation of the proposed solution, so it should be fixed and not so easy to edit for a mistake.
Can I do something to fix the duration time in a way that if someone want to use the gantt chart to move the start time of the task, the duration will be mantained?
Thanks,
Riccardo
Comments
-
Good question - there is not a way to prevent users from adjusting the duration by dragging the Gantt bars. I would recommend clicking in the body of the bar rather than the edges. The edges will change duration, while the body will change the start and end dates.
-
The problem is that usually the gantt bar is really short, so it's impossible to click in the middle of the bar. A great option could be to choose the gantt behaviour on click at the edge bar: change duration or translate start/end time.
Thank you Travis,
Riccardo
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives