Is there a way to embed a calendar you created from the calendar app without placing it as a widget in a dashboard?
Hello,
If you’re wanting to embed something in Smartsheet, using the Web Content widget in a Dashboard is the best way to do it.
Our Calendar App doesn't currently offer embed code capabilities that would allow you to embed the calendar anywhere outside of Smartsheet, but this would be a great opportunity to submit a Product Enhancement Request (you’ll find a link to this here in Community under Quick links on the right).
Is there an update whether the Calendar App offers embed code capabilities that would allow you to embed the calendar e outside of Smartsheet?
Is there any update regarding being able to embed the calendar app into another web page?
Any news on this feature? How can I embed a Calendar App Calendar on another site (SharePoint)?
@Alejandra Any updates on this one? I also heard a year ago that Calendar App was getting a make over. Is this still the case?
@Alejandra Any Updates on this? Would love to be able to embed the calendar app view in SharePoint. The Calendar view within smartsheet is about worthless when it is embedded in SharePoint.
There is a solution to this situation that involves merging the "Publish Link" from the Calendar App into the Embed Code from the sheet creating a new Embed Code URL to use in SharePoint. I have attached a PDF with the steps t take. Let me know if you have questions
Hi - We (@Jason.Miller@beigene.com and I), yesterday. LOVE IT!! Highly recommended!!
I know how to set up and create a Dynamic view and put this in WorkApps but what I don't know is how to share it with 600 people. In General Setting "Restrict view by current user is "Submitted by", 600 people can view their "Own" submissions. In Sharing Tab , "Shared Domain" if I add our work domain, " "abc.com", why do…
I'd like to integrate some of the task information from two totally different smartsheet schedules into the primary/main project schedule but not all of the tasks in the two different schedules. Is there a way to integrate just some of the tasks from the different schedules and also have predecessor relationships to tasks…
I have a large number of assets that have been provisioned through Control Center. I want to install a formula in one cell in a specific column. I thought I could update the template in the source folder of the blueprint and publish it, however, that functionality has been removed or I can't quite figure out how to do it.…