Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Predecessor numbers automatically updating
When I add new lines to the sheet, the predecessor numbers do not automatically update to the change in the number to the task to which it should be linked. How can I make sure they update as I edit the sheet?
Comments
-
Sandi,
Are you adding the new line at the end of the sheet? Then there is nothing to update and the predecessor won't be auto-filled like formatting or formulas.
Are you adding the new line somewhere in the middle or top (thus shifting the rows below it down)? Then the predecessors below it should change.
The only reason I can think that they would not would be if your dependencies had been disabled or the Predecessor column was misnamed.
Project Settings are found after showing the Gantt chart view in the upper left (the gear symbol)
Hope that helps.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 348 Global Discussions
- 199 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 455 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 282 Events
- 36 Webinars
- 7.3K Forum Archives