Make the duration of the task/milestone "0".
-
Thank you for your advice... I tried but I couldn't do it. I erased the start and end date, and then the task is completely gone!!!
If you know how to do, could you please be more specific??
Thanks a lot....
-
Dear Murat,
The diamond shape means that the specific row refers to a milestone, and as such it does not have "duration", so it should be '0' - as Chris wrote. You shouldn't have erased the start and end dates. Once duration is set to '0', they will automatically be set to the same dates, and the diamond will appear on the Gantt Chart.
Atus
-
To add a milestone (diamond icon) the start and end dates need to be the same date and the duration needs to be 0
-
Dear Atus,
Thank you very much for your explaining. I again tried it like you said. But, still it doesn't work....
I think I'm technology-disabled....
-
Check out this article on creating milestones: http://help.smartsheet.com/customer/en/portal/articles/516406-creating-a-milestone
And here is the section of the recorded webinar which shows how to set it up: https://youtu.be/GD7hgHNDeYQ?t=9m5s
-
Dear John,
Thank you very much... The text helped me a lot...
I found my fault.. I haven't opened the "Dependencies"!!!! (
Now, everything's fine...
Thank you and to Atus....
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives